The Commercial Property Compliance Calendar: Every Inspection Interval in One Place
- Annual: fire risk assessment review, extinguisher service, gas safety inspection, and alarm and emergency lighting servicing.
- Around every two years: the legionella risk assessment review, with monitoring in between.
- Every five years: the EICR for most commercial premises and the TM44 air conditioning inspection.
- Every ten years: the EPC, with the minimum E rating checked well before any sale or letting.
Most compliance failures are not decisions. They are dates that nobody owned. The extinguisher service lapsed because the contractor changed, the EICR was due in the year the facilities manager left, the EPC expired a month before the re-let. Running compliance as one calendar, rather than seven separate reminders, is the single cheapest improvement most buildings can make. Here are the intervals, where they come from, and how to put them together.
Annually
- Fire risk assessment review. The Order requires regular review and review on change; annual is the norm. See fire risk assessment.
- Fire extinguisher service to BS 5306-3, with extended service at five years (ten for CO2). See extinguisher servicing.
- Fire alarm and emergency lighting. Periodic servicing by a competent contractor, with monthly in-house tests recorded in the log book.
- Gas safety inspection of appliances, pipework and flues, recorded on a CP17 or CP42. No fixed commercial interval in law; annual is the accepted standard. See gas safety.
- Air conditioning servicing and F-Gas leak checks, with frequency set by the refrigerant charge.
Around every two years
- Legionella risk assessment review. ACoP L8 requires review when things change and at regular intervals; two years is common practice, with monthly or quarterly monitoring of temperatures and outlets in between. See legionella.
- PAT testing of moveable equipment in offices, with IT equipment on longer intervals and harsher environments on shorter ones. HSE sets no fixed interval. See how often to PAT test.
Every five years
- EICR. The accepted interval for most commercial premises, shorter for industrial, leisure and higher-risk uses, and the previous report states the recommended date. See EICR frequency.
- TM44 air conditioning inspection for systems over 12kW, required at least every five years. See air conditioning.
- Extinguisher extended service at five years for most types.
Get every date in one go
The free compliance check lists every duty on your property and gets you a quote for each, so the calendar starts from one visit.
Every ten years, and on events
- EPC. Valid for ten years, but the minimum E rating is checked at every letting, so look at it well before a lease event. See commercial EPC.
- Asbestos. The management survey is done once; the register and plan are reviewed regularly, commonly annually, and a refurbishment survey is needed before any works. See asbestos surveys.
- Planned maintenance survey. Not a statutory interval, but a PPM survey every three to five years keeps the capital programme honest.
Running it as one calendar
Put every duty in one register with the last date, the next date, the contractor and where the certificate is filed. Align visits where one contractor can do two things: EICR and PAT testing, extinguishers and alarm servicing, gas and air conditioning. Review the register at one fixed point each year, ideally before the insurance renewal, because that is when someone will ask. Our guide to a statutory servicing schedule shows how a maintenance contract can carry the whole programme.
Starting the calendar
If you are starting from nothing, the free compliance check gives you the list of duties for your building and a quote for each, so the first round of inspections can be booked together and the dates fall out of that.
Sources & further reading
- HSE: PAT, answers to popular questions — no fixed interval for portable appliance testing
- HSE: Legionnaires’ disease, ACoP L8 — review of the legionella assessment
- GOV.UK: air conditioning inspections for buildings — the five-yearly TM44 requirement
- GOV.UK: find an energy certificate — EPC validity and the register
External links open in a new tab. ComSurv is a matching service, not a firm of surveyors, and is not affiliated with these organisations. This article is general information, not legal, surveying or valuation advice; take advice on your specific situation.