Guides · New Premises

Fitting Out a Commercial Unit: Licence to Alter, Consents and Sign-Off

5 December 2026 · 9 min read

Key takeaways

  • The licence to alter is a negotiation, not a form. What it says about reinstatement decides your dilapidations bill at the end of the term.
  • Planning, building regulations and the lease are three separate consents. Passing one does not pass the others.
  • In a pre-2000 building, a refurbishment survey of the areas you will disturb is required before work starts. The landlord’s management survey is not enough.
  • You are the client under CDM 2015 from the moment you appoint a contractor. The duties are small on a small job, but they are yours.

The fit-out is the part of taking a unit that new tenants enjoy, and the part that creates the most expensive problems years later. Work that was never consented to has to be stripped out at lease end. Work that was never certified has to be inspected again. Work that disturbed asbestos nobody surveyed stops the job and empties the budget. Four permissions come before the first drill, and a file of certificates comes before you open. This guide puts them in order, as the detailed version of the fit-out section in our main checklist.

The four permissions, in the order to get them

Our main checklist lists the fit-out checks in one paragraph. Here is the order they have to happen in, because each one feeds the next.

  1. The lease: a licence to alter. Agreed first, because the landlord may refuse or condition the works, and because the landlord’s surveyor will often want to see the planning and building regulations position before signing.
  2. Planning permission, where the works change the outside of the building, the shopfront or the use.
  3. Building regulations approval, for anything structural, anything touching fire escape or compartmentation, new drainage or WCs, and most changes of use.
  4. Your insurer and the landlord’s building rules. Tell your insurer the works are happening. In a shopping centre or managed building, a fit-out guide and a permit-to-work system will apply on top of everything above.

Add one more before any of them: in a building built before 2000, the asbestos refurbishment survey, because its findings can change the design.

The licence to alter: what it is and what to negotiate

Most leases say you cannot make alterations without the landlord’s written consent, usually with a distinction between non-structural works that need consent and structural works that are prohibited outright. The consent, when given, is a formal document called a licence to alter, with drawings attached.

For works that are improvements, section 19(2) of the Landlord and Tenant Act 1927 says consent cannot be unreasonably withheld. It also lets the landlord attach conditions, and the three usual ones are:

  • Reinstatement. A requirement to remove the works and make good at the end of the term. This is where a large part of an office or retail tenant’s dilapidations bill comes from. Negotiate it item by item: partitions usually have to go, but a new WC, an upgraded electrical board or a better shopfront may be improvements the landlord is happy to keep. Get the position in writing in the licence, not in an email.
  • Fees. The landlord’s legal and surveying costs for considering and documenting the consent. Agree a cap.
  • Compliance and as-built information. An obligation to carry out the works to the drawings, in accordance with all consents, and to hand over as-built drawings and certificates on completion. Treat this as a checklist for the sign-off section below.

Our guide to section 18 of the 1927 Act explains how the end-of-term claim is capped, and why what the licence says about reinstatement matters so much to it.

Planning and building regulations

Planning. Internal works rarely need planning permission. External works often do: a new shopfront, a shutter, a flue or extract at roof level, external plant, and anything on a listed building or in a conservation area. Signs are controlled separately under the advertisement regulations. The Planning Portal’s guidance for shops covers the common cases, and our shop checklist walks through the sign.

Building regulations. Separate from planning and more often triggered by a fit-out. Approval is needed before you start for structural changes, new or altered escape routes and fire compartmentation under Approved Document B, new drainage and sanitary fittings, alterations to the entrance and access under Approved Document M, changes to heating and ventilation systems, and many changes of use. You can apply to the council’s building control or to an approved inspector, and the project ends with a completion certificate, which the landlord’s licence and your insurer will both expect to see.

If you serve the public, the fit-out is also where the Equality Act duty to make reasonable adjustments to physical features is cheapest to meet. Design the entrance, the counter and the WC for access now rather than retrofitting them after a complaint.

Asbestos: the refurbishment survey

In any building built before 2000, assume asbestos is present until a survey says otherwise. The landlord’s register, held under regulation 4 of the Control of Asbestos Regulations 2012, is based on a management survey, which only looks at what can be seen and reached. A fit-out goes behind ceilings, into risers and through walls, and for that the HSE’s HSG264 requires a refurbishment and demolition survey of the areas affected, which is intrusive and done before the contractor starts. Our guide to the refurbishment survey explains the scope, and the difference between the two surveys is worth five minutes before you brief the contractor.

The survey report, together with the register, forms part of the pre-construction information you must give every contractor under CDM. If the survey finds material in the way of the works, licensed removal has its own lead time and notification period. Get the survey done before the design is final.

Compliance Check

See what the unit needs before the fit-out starts

Run the free compliance check on the premises you are fitting out. You get the list of surveys and certificates the works will need, with a quote for each from a provider who covers your area.

Start the free check

CDM 2015: you are the client

The Construction (Design and Management) Regulations 2015 apply to every construction project, and a shop or office fit-out is one. As the business commissioning the work you are the client, and the duties are yours even if you have never heard of them.

  • Make suitable arrangements for managing the project, including enough time and resource for it to be done safely.
  • If more than one contractor will be on site at any time, which on a fit-out is almost always, appoint in writing a principal designer and a principal contractor. If you do not, you carry those duties yourself.
  • Provide pre-construction information: the asbestos register and survey, the existing services drawings, the fire strategy and anything else about the building that affects safety.
  • Make sure a construction phase plan exists before work starts and that welfare facilities are provided.
  • Notify the HSE if the project will last more than 30 working days with more than 20 workers at once, or exceed 500 person-days.

On a small fit-out the practical answer is to appoint a contractor who takes on the principal roles and to put the appointments in the contract. The point is to have it written down.

Party walls and neighbours

If the works involve a wall shared with the neighbouring unit, cutting into it for a steel, a new opening or a flue, or excavating near a neighbour’s foundation, the Party Wall etc. Act 1996 requires notice to the adjoining owner before work starts, with a dispute process and surveyors if they do not consent. The notice period runs to two months for some works, so it belongs in the programme. Our guide to the party wall schedule of condition explains the record that protects both sides.

The lease and the estate rules will also set hours for noisy work and deliveries, and the landlord of a multi-let building will usually require you to use their permit-to-work system for hot works and for anything touching the fire alarm or sprinklers.

Sign-off: the certificates you must have before you open

The fit-out is not finished when the contractor leaves. It is finished when this file exists.

  • Building control completion certificate for any work that needed approval.
  • Electrical Installation Certificate for new circuits and a Minor Works Certificate for small changes, both to BS 7671. File them with the EICR, because without them the next inspector has to treat the new work as unknown.
  • Commissioning certificates for the fire alarm, the emergency lighting and any sprinkler or suppression system, from the installer.
  • Gas commissioning and the catering gas certificate for any new gas appliances, from a Gas Safe engineer with the right categories.
  • The asbestos survey, any removal certificates and the air clearance, with the register updated to show what was removed.
  • As-built drawings, handed to the landlord under the licence and kept with the lease.
  • An updated fire risk assessment, because the layout has changed. The assessment you did on the day you took the keys is out of date the day the partitions go up.
  • Photographs of every room, before and after.

Our guide to compliance records sets out how to keep the file, and tenant compliance responsibilities covers the duties that start the day you open.

What this means at lease end

Every document in the file above is a document you will want when the landlord’s surveyor serves a schedule of dilapidations. The licence shows what was consented and what has to be reinstated. The certificates show the work was done properly. The photographs and the schedule of condition show what the unit looked like before you touched it. Together they are the difference between a claim you can answer and one you simply pay.

Sources & further reading

Questions

Frequently asked questions

What is a licence to alter?

It is the landlord’s formal written consent to the alterations you want to make under a lease that prohibits alterations without consent. It attaches drawings, sets conditions such as reinstatement at the end of the term, and usually requires you to hand over as-built drawings and certificates on completion.

Can a landlord refuse consent for a fit-out?

For works that are improvements, section 19(2) of the Landlord and Tenant Act 1927 says consent cannot be unreasonably withheld, but the landlord can attach reasonable conditions, including reinstatement and payment of their costs. Structural works are often prohibited outright by the lease, in which case the landlord can refuse.

Do I need building regulations approval for a shop fit-out?

For many fit-outs, yes. Structural changes, new or altered escape routes, fire compartmentation, new drainage and WCs, changes to the entrance and access, and many changes of use all need approval before you start. Purely cosmetic work does not. You get a completion certificate at the end, which the landlord and your insurer will expect to see.

Do I need an asbestos survey before a fit-out?

In a building built before 2000, yes. The landlord’s management survey only covers what can be seen and reached. Before work goes behind ceilings or through walls, a refurbishment and demolition survey of the areas affected is required under the HSE’s HSG264, and its report must be given to the contractor as pre-construction information.

Does CDM apply to a small office or shop fit-out?

Yes. The Construction (Design and Management) Regulations 2015 apply to every construction project, and the business commissioning the work is the client. With more than one contractor on site you must appoint a principal designer and a principal contractor in writing, provide pre-construction information and make sure a construction phase plan exists before work starts.

What certificates do I need after a commercial fit-out?

A building control completion certificate for any approved work, Electrical Installation Certificates for new circuits, commissioning certificates for the fire alarm, emergency lighting and any suppression system, gas commissioning records, the asbestos survey and any removal and clearance certificates, as-built drawings for the landlord, and an updated fire risk assessment.